if 450 workers can dig a canal 6km long 4m wide and 2m deep in 30 days, what length of a canal 5m wide 2.5m deep can be dug by 500 workers, all working at the same rate
Answers
Answered by
4
Answer:
10.42
Step-by-step explanation:
This is a question on ratio rates and proportion.
To get the length you first arrange the values that you have
Workers length Width depth days
450 6. 4. 2. 30
500 ? 5 2.5. 30
This question is on direct proportion because an increase in one variable cause an increase in the other variable
Therefore first you take
500 × 6 ÷450 = 6.667 cm
An increase in length causes an increase in the width therefore
6.66 × 5 ÷4 = 8.334cm
8.334 × 2.5 ÷2 =10.42cm