If 45men can do piece of work in 49 days, in how many days 35men do it
Answers
Answered by
0
Answer:
35 men can do the same work in (49*45) / 35 days = 63 days.
Answered by
1
Answer:
45 men = 49 Days
35 men = y
35y = 45×49
y = 2205 ÷ 35
y = 63
35 men do it in 63 Days.