Math, asked by gmona5949, 7 months ago

If 45men can do piece of work in 49 days, in how many days 35men do it​

Answers

Answered by twinkle0905
0

Answer:

35 men can do the same work in (49*45) / 35 days = 63 days.

Answered by Anonymous
1

Answer:

45 men = 49 Days

35 men = y

35y = 45×49

y = 2205 ÷ 35

y = 63

35 men do it in 63 Days.