Math, asked by priyanka18885, 8 months ago

If 48 men can dig a trench in 14 days, how long will 28 men take to dig a similar trench?​

Answers

Answered by saksham16358
10

Answer:

From the question,

48 men can dig a trench in 14 days

1 man can dig a trench in =(14×48) days .. [ less men, more days]

∴28 men can dig a similar trench in =(14×48)/28

=24 days ...[ More men, less days]

Hence, the required number of days for 28 men to dig a trench =24.

Answered by Anonymous
1

Answer:

your answer is 24

Step-by-step explanation:

Answer by @MrMysteryy