Math, asked by mannha, 5 hours ago

If 48 men
can do, a piece of work in 24 days, in how many days 36 men will complete the
same work?

Answers

Answered by babymahanta66
1

Answer:

=> 48/24=36/x

=> x=36×24/48

=> x=72

Answered by uietofficecsjmu
1

let the work done by 36 men as x

36*x =48*24

x =48*24/36

= 72 days