If 48 men
can do, a piece of work in 24 days, in how many days 36 men will complete the
same work?
Answers
Answered by
1
Answer:
=> 48/24=36/x
=> x=36×24/48
=> x=72
Answered by
1
let the work done by 36 men as x
36*x =48*24
x =48*24/36
= 72 days