If 48 workers can reap a field in 9 days and the work is to be completed in 6
days, the extra workers required are

Answers

Answered by riddhima4097
0

Answer:

In 9 days,no. of workers = 48

In 1 day,no.of workers=48×9

So,in 6 days no.of workers =48×9/6

=72 workers Ans....

HOPE IT HELPS

Answered by XxShAnTaNuxX
0

Question ⤵️

If 48 workers can reap a field in 9 days and the work is to be completed in 6 days, the extra workers required are ??

A᭄ɴsᴡᴇʀ ⤵️

=> 48 workers = 9 days

=> 1 Day = 48 × 9

 =  > 6days \:  =  \frac{48 \times 9}{6}  \\  =  >   \frac{48 \times 3}{2}  \\  =  > 24 \times 3 \\  =  > 72 \: workers

Total =>

72 workers

=>> 72 - 48

=> 24 more workers needed