If 48 workers working for 8 hours a day can finish building a wall in 9 days If each worker works for 6 hours a day, find the number of workers to finish the same wall in 8 days
Answers
Answered by
0
Answer:
72 workers
Step-by-step explanation:
In 9 days working 8 hours need 48 workers
In 1 day working 1 hour need 48 × 9 × 8 workers
(since days and hours are inverse variation with workers so we multiplied to find unit day & hour)
In 8 days working 6 hours need (48×9×8)/(8×6)=72
Ans: 72 workers
Similar questions