if 49 men can do a piece of work in 49 days in how many days will 35 men do it
Answers
Answered by
4
35 days
Step-by-step explanation:
49 men do 1 work in 49 days.
1 man will do 1 work in 49/49 = 1 day.
35 men will do 1 work in 1 × 35 = 35 days.