If 5 boys can finish a piece of work in 8 days how many days will 6 boys take to the same piece of work
Answers
Answered by
0
Answer:
6.67 days (approx.)
Step-by-step explanation:
It is inverse proportion,
No. of days needed by 5 boys=8
No. of days needed by 1 boy= 5×8
=40
No. of days needed by 6 boys= 40÷6
= 6.67
Ans. 6.67 days (approx.)
Please mark as brainliest
Answered by
0
Step-by-step explanation:
men Days
5 8
6 ? (A)
? is taken as A
5×8 = 6×A
40 = 6× A
A = 40 ÷ 6
A= 6.5
HOPE YOU LIKE THE ANSWER..
MARK ME AS BRAINLIST...