If 5 Boys complete a work in 10 days , then 1 boy will complete the work in how many days ?
Warning:- if you will post answer without formula your answer will be reported
Answers
Answered by
0
Answer:
working days =10
boys=5
working day for 1 boys=10/5
work day for one boy =2 days