if 5 men can finish a piece of work in 12 days, how long will it take 3 men to do the same job pls pasagot need kona bukas thanks
Answers
Answered by
1
Answer:
7.2 days
Step-by-step explanation:
5 men finish work in = 12 days
1 man can finish work in = 12÷5=2.4 days
3 men can finish work in = 2.4×3=7.2
Answered by
0
Answer:
20 days
Step-by-step explanation:
inverse variation
no.of men no.of days
5 12
1 5x12
1
= 60 days
3 3
60
= 20 days
therefore 3 men will take 20 days to complete the work