If 5 men can paint a room 50 m long, 6 m high and 13 m wide working 10 hours
per day in 6 days, then how many days of 9 hours each will 10 men need to paint
a room 40 m long, 7 m high and 10 m wide. (Assume all the walls and ceiling are
painted leaving the floor)
Answers
Answer:
25*2=50/2=25*3=75/25=3
Step-by-step explanation:
Given:
Dimensions of the room = 50x6x13 m
time taken by 5 men to complete the task = 6 days
number of hours of work each day = 9 hours
To find:
Time taken to complete the second room by 10 men.
Solution:
total surface area of the first room painted = 50 x 13 + 2( 50 x 6 + 13 x 6)
= 650 + 2( 300 + 78)
= 1406
Number of days taken to complete the task = 6 days
number of hours worked per day = 10 hours
total number of hours taken = 60 hours
Time taken by 5 men to paint 1 area = hours
Now,
Dimensions of the second room = 40 x 7 x 10
Area of the second room to be painted = 40 x 10 + 2(40 x 7 + 7 x10)
= 400 + 2(280 + 70)
= 1100
Number of hours taken by 5 men to paint 1100 area = x 1100
= 46.94 hours
So, time taken by 10 men to complete this task = = 23.47 hours
So, if 9 hours of work is done each day, number of days required =
= 2.6 Say 3 days
Therefore, 3 days are required to complete the task.