Math, asked by varun2004kushwah, 6 months ago

If 5 men each a work in 5 day. How many men can finish it in 2 days​

Answers

Answered by AryanDubey124
1

Answer:

12.5 or 13 men's

Step-by-step explanation:

5 men do it in 5 days

so we have to do it in 2 days

so we need 5×5/2

= 12.5 men...

Answered by Anonymous
0

Given,

5 men can finish a piece of work in 5 days working together.

Required,

No. of men than can finish it in 2 days.

If, the number of men increases, the no. of days required to finish the work decreases in a proportional manner, assuming that each man does an equal amount of work.

So, this is a case of inverse proportion.

Let no. of men required to finish it in 2 days be X men.