If 5 men or 10 boys can complete a work in 5 days in how many days will 4 men and 17 boys completed
Answers
Here 5 men=10 boys
1 men= 2 boys
If 10 boys can do it in 5 days,
No. of boys is inversely proportional to the no. of days.
4 men and 17 boys, 4×2+17 boys= 25 boys
((10 x 5)/25) = 2 Days
Answer is 2 days!
The number of days taken by 4 men and 10 boys to complete the work is 2 days.
GIVEN
Number of days taken by 5 men = 5 days
A number of days taken by 10 boys = 5 days.
TO FIND
The number of days taken by 4 men and 17 boys to complete the work.
SOLUTION
We can simply solve the above problem as follows -
Let the total magnitude of the work be, W.
Let The working rate of 1 boy = R
So, the working rate of 1 man = 2R.
So,
Work = Days × working rate
5 × 2R × 5 = W. (equation 1)
Let x be the number of days taken by 4 men and 17 boys to complete the work.
So,
(4× 2R + 17×R)x = W
(8R + 17R)x = W (equation 2)
Since the magnitude of work is the same,
So,
5 × 2R × 5 = (8R + 17R)x
5 × 2R × 5 = 25Rx
We can also write it as-
5×2R×5 = (5×5)Rx
Solving for x,
x = 5×2R × 5 /5×5 × R
x = 2 days.
Hence, The number of days taken by 4 men and 10 boys to complete the work is 2 days.
#Spj2