If 5 men working 9 hrs a day can reap a field in 16 days in how many days will 18 men reap the field working 8 hrs ad ay
Answers
Answered by
44
Solutions :-
Given :
M1 = 5 men
T1 = 9 hours
D1 = 16 days
M2 = 18 men
T2 = 8 hours
We know that,
M1 × T1 × D1 = M2 × T2 × D2
=> 5 × 9 × 16 = 18 × 8 × D2
=> D2 = (5 × 9 × 16)/(18 ×8) = 5
Hence,
If 18 men working 8 hrs a day can reap a field in 5 days
Given :
M1 = 5 men
T1 = 9 hours
D1 = 16 days
M2 = 18 men
T2 = 8 hours
We know that,
M1 × T1 × D1 = M2 × T2 × D2
=> 5 × 9 × 16 = 18 × 8 × D2
=> D2 = (5 × 9 × 16)/(18 ×8) = 5
Hence,
If 18 men working 8 hrs a day can reap a field in 5 days
Answered by
7
We will use Chain Rule to solve this question.
According to Chain Rule, the work efficiency remains constant.
• = Constant
• Here W = Work Done, WF = Workforce, T = Time.
Let the number of days needed be 'x'.
Applying Chain Rule,
Or, x = 5 Days (Answer)
According to Chain Rule, the work efficiency remains constant.
• = Constant
• Here W = Work Done, WF = Workforce, T = Time.
Let the number of days needed be 'x'.
Applying Chain Rule,
Or, x = 5 Days (Answer)