Math, asked by sarikashukala1978, 6 days ago

if 5 person takes 4 day so if 4 person will be doing then how many days will it take

Answers

Answered by kalash9607
1

Answer:

Four men take 4 days to complete a task. It means the task requires 4*4 = 16 man-days. So if you engage, 2 men they will complete it in 16 man-days/2 men = 8 days.

Answered by parasjain0203
0

Answer:

3.2 days

Step-by-step explanation:

5 person takes to complete = 4 days

1 person will take = 4/5

So 4 person will be doing = (4*4)/5 = 3.2 days