Math, asked by P4u, 3 months ago

if 5 workers build a wall in 48 days how many days will 24 workers take to complete the wall​

Answers

Answered by swati6553
1

Answer:

24 workers will take 10 days to complete the wall.

Step-by-step explanation:

5 workers build a wall in 48 days

1 worker builds a wall in (48×5) days = 240 days

24 workers build a wall in (240÷5) days = 10 days

Answered by gayatrilove
1

Answer:

5 workers=48 days

24 workers=?

48×5=240

24×?=240=240÷24=10 days

So, 24 workers will take 10 days to complete the wall.