Math, asked by mirabaiwagh21, 9 months ago

If 5 workers take 12 days to weed a field how many days will 6 workers take? ​

Answers

Answered by yogichaudhary
4

5 workers take 12 days to weed a field.

1 worker takes = 1/5 × 1/12

= 1/60

In one day 6 workers can weed = 6/ 60

= 1/10

______________________________________

Hence , 6 workers take 10 days to weed the field ^_^hope it helps!!!

@GameChanger

Answered by sonigupta251279
1

Answer:

10 days = 240 hrs.

Step-by-step explanation:

Let the no. of hours be x.

No. of hours No. of workers

288 | 5 ⬆

x ⬇ 6 |

X/288 = 5/6

X = 5/6 * 288

X = 5 * 48

X = 240 hrs

X = 10 day

I have converted the unit day into hrs. bcoz it is easy to do it like that

I have used Criss cross method which is very easy to solve the questions of direct and indirect inverse ....

hope you liked it ....

Similar questions