If 50 men can do a piece of work in 18 days. In how many days will 45 men do it
Answers
Answered by
0
Answer:
15days
Step-by-step explanation:
because 50days are the men
Answered by
0
Step-by-step explanation:
m men and d no. days taken by them to finish the work are inversely proportional
so m1d1 = m2d2
50×18 = 45×x
x= 50×18/45 = 20 days