Math, asked by rubikumari2000, 5 months ago

If 50 men can do a piece of work in 18 days. In how many days will 45 men do it​

Answers

Answered by sarthakkkkkkkkk
0

Answer:

15days

Step-by-step explanation:

because 50days are the men

Answered by bson
0

Step-by-step explanation:

m men and d no. days taken by them to finish the work are inversely proportional

so m1d1 = m2d2

50×18 = 45×x

x= 50×18/45 = 20 days

Similar questions