if 50 men can do a piece of work in 20 days how many men will do it 10 days
Answers
Answered by
1
20 /2 is 10
so , 50/ 2 -25
the answer is 25 men
mark me as brainlist please....
Answered by
1
Answer:
100 men.
Step-by-step explanation:
as 50 men do the work in 20 days so..
work done by 50 men in 1 day = 1/20
work done by 1 man in 1 day = 1/20*50
= 1/1000
let X men will do the work in 10 days so..
work done by X men in 1 day = 1/10
work done by 1 man in 1 day = 1/10*X = 1/10X
As the work is same.. so,
1/1000 = 1/10X
10 X = 1000
X = 100
so 100 men will do the work in 10 days. I hope it will help you.