If 50 men can do two thirds of a piece of work in 30 days then how much work can be done by 45 men in 20 days
Answers
Answered by
3
Answer:
of a piece of work can be done by 45 men in 20 days.
Step-by-step explanation:
In order to solve this problem, the following formula is required.
m₁d₁t₁w₂ = m₂d₂t₂w₁
where, m₁, m₂ = number of men.
d₁, d₂ = number of days required.
t₁, t₂ = amount of time required, in hr, min or sec. (if mentioned)
w₁, w₂ = work done.
- NOTE: The left hand side of the formula contains w₂ and the right hand side contains w₁, unlike the m,d or t.
Thus, in the given question, we can see that,
- m₁ = 50 men, d₁ = 30 days, w₁ =
- m₂ = 45 men, d₂ = 20 days, w₂ = ?
Let w₂ = x.
Using the above values in the formula, we have,
50 * 30 * x = 45 * 20 *
⇒
⇒
⇒
⇒
Thus, in 20 days, 45 men can complete of the work.
Similar questions