if 52 men can do a piece of work in 35 days ,in how many days 28 men will do it

Answers

Answered by itcjohithvinayak
49
It takes 65days for 28men to complete the waork
Answered by nikhita
151

52 men take 35 days to complete a piece of work

1 man takes (52 x 35) = 1 820 days

28 men take (1 820/28) = 65 days to complete the same piece of work.