if 52 men can do a piece of work in 35 days, in how many days 28 men will do it ?

Answers

Answered by Shhii
11
Hey.... ♥
35 days ---------> 52 men comp...
1 day -------> 52/35
28 days ---------> 52*28/35 = 41. 6 days aproxx..
Answered by nirmalsai2263
4

52 - 35

28 - ?

cross multiply......

52 * ? = 28 * 35

? = 980 / 52

? = 18