If 52 men can do a piece of work in 35 days, in how many men will do it in 14 days?
Answers
Answered by
0
Step-by-step explanation:
52/35=x/14
x=52×14/35
men needed will be 20.8 means 21 approx.
Answered by
2
Answer:
52/35=x/14.
x=52×14/35.
x=21.