if 52 men can do piece of work in 27 days , long will 39 men take to complete the same work
Answers
Answered by
2
Answer:
36 days
Step-by-step explanation:
It is an indirect variation
So, time taken by 52 men to do a piece of work = 27 days
Time taken by one man to complete the work = 27×52 = 1404 days
Time taken by 39 men to do do the same work =
Answered by
0
Answer:
39 men
Step-by-step explanation:
For the work to be done in 52 days , men required = 27 days
now 27*52 = 36*(no. of men)
so no. of men = (52/27)*36 = 39 men.