If 54 men can do a piece of work in 42 days. How many men is needed to do it in 14 days ?

Answers

Answered by Shubhampro112
0

Answer:

63 men required to finish the work in 42 days.

Step-by-step explanation:

Answered by vsrihari2029v
1

answer. 27.

Step-by-step explanation:

answer. 27.