if 54 men can finish a piece of work in 49 days, then how many men will be needed to finish it in 42 days?
Answers
Answered by
14
Answer:
in 49 days a work is finished by=54men
in 1 days .........................................=54×49 men
in 42 days .....................................=54×49\42
=63 men
solve 54×49\42 and u will get 63 answer.
Answered by
3
In 49 days = 54 men
In 1 day = 54/49
Therefore, In 42 days = 54 / 49 × 42, i.e.
46 2/7 days.
This is ur answer plz follow it...all the best...