Math, asked by Ashantosingh680, 1 year ago

If 56 man can do a piece of work in 42 days how many men will do it in 14 days

Answers

Answered by ItzMysticalBoy
11
Number of men can do a piece of work in 42 days=56 men

Number of man can do a piece of work in 1 day=56×42 men

Number of men can do a piece of work in 14 days =56×42/14
= 168men

shaktimaan95: goof
shaktimaan95: sorry good