If 56 men can complete paving a stretch of road in 18 days, how long will 24 men take to complete the same work?
Answers
Answered by
7
Take proportional
56:18::24:x
That is :-
56 ×24 = 18 × x
1344 = 18x
1344/18 = x
74.6 = x
They need to take 75 days (approx)
56:18::24:x
That is :-
56 ×24 = 18 × x
1344 = 18x
1344/18 = x
74.6 = x
They need to take 75 days (approx)