If 56 men can complete paving a stretch of road in 18 days, how long will 24 men take to complete the same work?

Answers

Answered by devadakshan
7
Take proportional

56:18::24:x

That is :-

56 ×24 = 18 × x
1344 = 18x
1344/18 = x
74.6 = x

They need to take 75 days (approx)