Math, asked by tuhicomp, 11 months ago

if 56 men can do a piece of work in 42 days how many men will do it in 14 days​

Answers

Answered by rose5694
3

Answer:

168 days ............

Answered by BrainlyPhantom
2

Here the no. of people x and no. of days y a are varying inversely.

x1 = 56. y1 = 42

x2 = ? y2=14

x1y1 = x2y2

56× 42 = x2× 14

56×42 ÷ 14

= 168

Hope it helped you.