If 56 men can do a piece of work in 42 days. How many men will do it in 14 days?

Answers

Answered by js403730
2

Answer:

Answer:

168 men

Step-by-step explanation:

We are given that  56 men can do a piece of work in 42 days

1 man can do work in days =

Let the number of men be x who completes work in 14 days

So,x men can do work in =14 days

So, Number of men required to do work in 14 days =

 = Hence 168 men can complete work in 14 days.

Answered by abdullah060903112
0

168 men can complete work in 14 days.