Math, asked by seesaw, 1 year ago

if 56 men can do a piece of work in 42 days, how many men will do it 14 days

Answers

Answered by Yashasvi11
86
it is a case of inverse variation
56×42÷14=168
Answered by wifilethbridge
95

Answer:

168 men

Step-by-step explanation:

We are given that  56 men can do a piece of work in 42 days

1 man can do work in days = 56 \times 42=2352

Let the number of men be x who completes work in 14 days

So,x men can do work in =14 days

So, Number of men required to do work in 14 days = \frac{2352}{14}

                                                                                     = 168

Hence 168 men can complete work in 14 days.