If 6 boys can do a piece of work in 5 days, how
many boys will be required to get the same work
done in 2 days?
12
how
Answers
Answered by
2
Answer:
15
Step-by-step explanation:
6×5=30
30÷2
=15 boys
so the answer is 15
Similar questions