If 6 boys can finish a work in 18 days, how long will 18 boys take to finish the same work?
Answers
Answered by
3
Answer:
if 6 boys can finish a work in 18 days 3 boys can finish the work in 6.75 days
Answered by
11
Answer:
6 days.
Step-by-step explanation:
6 boys took 18 days
1 day work can be completed by 6/18 boys.
No. of days taken for 18 boys t complete the same work = 6/18 x 18
= 6 days