If 6 man and 9 women can do a piece of work in 15 days,how long will 12 women and 6 men take to do it ?
Answers
Answered by
1
Answer:
6man do work= 15 days
1 man do work=15/6
6 men do work=(15/6)*6
=15 days
9women work=15 days
1 women work=15/9
12 women work=(15/9)*12
= 20 days
now 6 men and 12 women work=15+20=35 days (ans)