Math, asked by Vaishnavi572, 1 year ago

If 6 men and 8 boys can do a piece of work in 10 days while 26 men and 48 boys can do the same in 2 days, the time taken by 15 men and 20 boys in doing the same type of work will be?

Answers

Answered by KabirKhanuja
8

Answer:

4 days

Step-by-step explanation:

if 6 men and 8 boys do the work in 10 days-

14 people → 10 days

35 people → x days

therefore, x= 14×10/35

as it is inverse proportion!!!

x= 4

therefore,answer is 4 days.

Fine!!!!