Math, asked by himanshusharmagaur03, 10 months ago

If 6 men can do a peice of work in 3 days. In how days will 18 men do the same
work?​

Answers

Answered by anuj4696
0

Answer:

18 men complete the work in 1 day.

Answered by Anonymous
11

Answer:

9 days

Step-by-step explanation:

Given,

6 men can do the work in = 3 days

So by using unitary method, we get,

1 men can do the work in = 3/6 days

Then,

18 men can do the work in = 3/6 × 18 days = 3 × 3 = 9 days

Hence, 18 men can do the work in 9 days.