If 6 men can do a piece of work in 10 days. then 4 men will complete the same work in
Answers
Answered by
2
Answer:
6x10 =60
so 60/4 =15
Therefore, 4 men can complete the work in 15 days
Answered by
1
Hello inderjitthaman339 !
Answer:
15 Days
Step-by-step explanation:
Given :
6 men can do a piece of work in 10 days.
Procedure :
The meaning of '6 men can do a piece of work in 10 days' is that the job requires 6 × 10 = 60 men•days.
Hence if 4 men were to do the same job, it will take (60 men•days)/4 men = 15 days.
Hence it will take 15 days for 4 men to complete.
(OR)
As this is clearly an example of inverse proportion, i.e. more the men, less the time they take to complete the work.
Hence
Here,
= 6 men.
= 10 days.
= 4 men.
=>
=> = 10 × (3/2) days
Hence = 15 days.