if 6 men can do a piece of work in 12 days working 8 hours a day how many men are required to complete the same work in the same number of days working 6 hours a day
Answers
Answered by
1
Answer:
if 6 men can do a piece of work in 12 days working 8 hours a day how many men are required to complete the same work in the same number of days working 6 hours a day
Answered by
0
Answer:
6 men can do work in= 12 days
work done in =8hrs per day
let men be m1 and m2 day be d1and d2 and hour be h1 and h2
m1*d1*h1=m2*d2*h2
6×12×8=m2×12×6
576=m2×72m2=576/72
m2=8