If 6 workers build road in 4 days, how
many days will 3 workers take to build
the same road?
Answers
Answered by
0
Answer:
8 days
Step-by-step explanation:
Please mark me as a brainliest and please follow
Answered by
0
Answer:
by inverse property
Step-by-step explanation:
no. of workers 6 3
no. of days 4 x
6 3
4 x 4 x 6/ 3
8 days
hope it helps you