If 6 workers can build 4 cars in 2 days, then how many days would it
take 8 workers to build 6 cars?
Answers
Answered by
6
Answer:
9/4 days
Step-by-step explanation:
We know the rate of 6 workers is 4/2 = 2 cars/day. We can create a proportion to determine the rate of the 8 workers. Thus, it will take 8 workers 6/(8/3)= 18/8 = 9/4 days to build 6 cars.