If 6 workers can construct a wall in 4 days,how many days wilo 4 workers,working at the same rate,take to construct the wall?
Answers
Answered by
8
Answer:
Hope it helps you.....(✿◕‿◕✿)
Step-by-step explanation:
If the number of workers decreases, the time to taken built the wall increases in the same proportion. Clearly, number of workers varies inversely to the number of days.
So here, x1 / y1 = x2 / y2 where
x1 = 6 workers , y1 = 4 days
x2 = 4 workers , y2 = ? days
Substitute,
6 / 4 = y2 / 4
y2 = (6 x 4) / 4
y2 = 6 days
Please mark as brainliest if it really helps you...❤❤❤