Math, asked by garggarg0402, 7 months ago

If 6 workers can construct a wall in 4 days,how many days wilo 4 workers,working at the same rate,take to construct the wall?​

Answers

Answered by Anonymous
8

Answer:

Hope it helps you.....(✿◕‿◕✿)

Step-by-step explanation:

If the number of workers decreases, the time to taken built the wall increases in the same proportion. Clearly, number of workers varies inversely to the number of days.

So here, x1 / y1 = x2 / y2 where

x1 = 6 workers , y1 = 4 days

x2 = 4 workers , y2 = ? days

Substitute,

6 / 4 = y2 / 4

y2 = (6 x 4) / 4

y2 = 6 days