Math, asked by asthaankita1244, 10 months ago

If 6 workers can paint a home in 24 hours how many workers will be required to do same work in 18 hours

Answers

Answered by Mithun721
0

Answer:

3 workers

Step-by-step explanation:

Given:

16 workers can do the work in 24 hours

To Find:

Workers in 18 hrs

Solution:

6 workers = 24 hrs

6 : 24 = x : 18

= 4hrs

Answered by nandarak4
1

There is a shortcut for this..

6 workers - 24 hr

x workers - 18 hr

  x = (6 * 24)/18

  x = 8 workers