if 60 boys can do a piece of work in 15 days, then in how many days will 50 boys do it?
Answers
Answered by
3
Answer:
18days
60 boys can do a piece of work in 15days
1 boy can do a piece of work in 15*60days
50 boys can do a piece of work in (15*60)/50days=18days.
Answered by
160
Answer:
50 boys can do that work in 18 days
Given :
- 60 boys can do a piece of work in 15 days
Find :
- how many days will 50 boys do that work
Step-by-step explanation:
60 boys = 15 days
50 boys = X
using direct proportion method,
60 boys × 15 /50
= 6 × 3
= 18 days
hence,50 boys can do that work in 18 days