if 60 people can do the work in 180 days then 120 people can do the work in how many days
Answers
Answered by
1
Answer:
90 days to do the work for 120 people
Answered by
1
Step-by-step explanation:
By Formula
M1 × D1 = M2 × D2
60×180 = 120×X
X=90