if 63 workers can do a peice of work in 30 days , in how many days will 42 workers will complete the same work in how many day
Answers
Answered by
3
Answer:
Less workers will take more time, obviously. With 27/63 portion of the work force, the work time will increase by 63/27. So:
63/27 x 42=98 days
Answered by
5
Answer:
63 Workers in 30 days.
1 worker in (30÷63) days.
Therefore, 42 workers in (30÷63)× 42 days.
= 20 Days
So, 42 workers will complete the same work in 20 days.( Answer)