Math, asked by suhani051107, 16 days ago

If 64 men can do a job in 20 days, how many men will be needed to complete the work in 16 days?​

Answers

Answered by Hellion
51

\huge \bf \underline{ \underline{Question}}

If 64 men can do a job in 20 days, how many men will be needed to complete the work in 16 days?

\huge \bf \underline{ \underline{Solution}}

Let us consider the number of men as 'x'.

We'll solve this using Unitary Method.

 =  \frac{64}{16} : \frac{x}{20}

 =  \frac{64}{16} = \frac{x}{20}

 =  4 = \frac{x}{20}

 =  80 = {x}

━━━━━━━━━━━━━━━━━━━━━━━━━

\mathtt{Final \ answer = 80 men}