Math, asked by kod345, 2 months ago

If 7 boys can complete a job in 21 days, how long will 21 boys take to complete the job?

Answers

Answered by amanraj56
0

Step-by-step explanation:

M1×D1 = M2×D2

7×21 = 21×X

7= X

hence 21 boys can do it in 7 days

#666

Answered by ItzShraddhu
1

in 3 days

KRDO MUJHE FOLLOW.....FRNDS...

Similar questions