If 7 Men can complete a work in 52 days.In how many days will 13 men finish the same work?
Answers
Answered by
0
Step-by-step explanation:
7 men=52 days
1 men = 52/7 days
13 men = 52/7×13
=676/7
=96.57
=97(Approx)
Therefore 13 men can complete the work in 97 days