if 7 typist typing 7 hours in a day (at equal speed) take 9 days to type the manuscript of a book, then in how many days will 3 typist working 3 hours in a day take to do the same job??​


Anonymous: really
Anonymous: ohk
Anonymous: babye dear
Anonymous: see you
Anonymous: have a great day tomorrow
anjanajadav: he is good
Anonymous: are
Anonymous: ohk
Anonymous: i Know
Anonymous: ba bye now

Answers

Answered by preeti9578
10

Answer:

Step-by-step explanation:

No of typists : 7

No of Hrs/day;7

No of days : 9

Total Working Hours Req for the job : 7*7*9 =441Hrs

Now,

No of typists : 3

No of Hrs/day : 3

Assume ’N’ - Required Days

So,

N* 3*3 = 441

N=49 Days

Answered by ltzSweetAngel
3

The "typist hours" are the same in both cases, which gives you an equation 7*7*9 = 3*3*days, Solve it for "days".

Answer. 49 Day's