If 7 worker complete their work in 16 days then how many days 4 worker complete the work?
Answers
Answered by
34
Fᴏʀᴍᴜʟᴀ ᴜsᴇᴅ :-
➺ If M1 men can do W1 work in D1 days working H1 hours per day and M2 men can do W2 work in D2 days working H2 hours per day, then :-
❦❦ (M1*D1*H1)/W1 = (M2*D2*H2)/W2 ❦❦
Sᴏʟᴜᴛɪᴏɴ :-
Given That,
→ M1 = 7 workers
→ D1 = 16 Days.
→ M2 = 4 workers
→ D2 = x Days.
Putting all values in formula now, we get :-
→ 7 * 16 = 4 * x
Dividing both sides by 4,
→ 7 * 4 = x
→ x = 28 Days. (Ans.)
Hence, 4 workers complete same work in 28 Days..
Answered by
6
If 7 worker complete their work in 16days ,then how many days 4 worker complete the work?
M1 = 7 workers.
D1 = 16days.
M2 = 4 workers.
D2 = x
Now,
Therefore,4 workers completed the work in 28 days.